Old Business#2021-0136
Jun 21, 2021
Possible Consideration Engineer Todd Parsons was present for the application and briefly described the plans. He identified the application as a minor modification to one approved by the Commission earlier in the year. Proposed changes include minor construction details such as describing the dimensions of crushed stone to be used. A generator has been added and the geothermal well field expanded. The HVAC for the field house demanded more wells than originally anticipated. Mr. Parsons identified that the construction activities would be occurring hundreds of feet away from the nearest wetlands. The structure was expanded by a cumulative 800 square feet for two reasons. The structural engineers determined that a pre-engineered structural system would be more fiscally efficient to construct and the geothermal mechanicals required additional space. DEEP and TAHD have reviewed and approved of the modified plans.